In the program since Dec 2023
Scranton to New York
PennDOT reports Step 2 work with the Federal Railroad Administration: a Service Development Plan, not another local feasibility sketch.
Scranton and Reading entered the federal passenger-rail pipeline in 2023. The Lehigh Valley is still outside it, working through a local study instead of a federal service plan. Here is what happened, what it costs us, and what you can do this week.
Time since the window closed with no Lehigh Valley application
Three Pennsylvania corridors wanted service. Two got into the federal program in December 2023 and are now writing Service Development Plans with the Federal Railroad Administration. One is still studying.
2026. Scranton and Reading: Writing the service plan. Lehigh Valley: Phase II local study, 12 to 16 months.
In the program since Dec 2023
PennDOT reports Step 2 work with the Federal Railroad Administration: a Service Development Plan, not another local feasibility sketch.
In the program since Dec 2023
The Schuylkill River Passenger Rail Authority’s public record shows Step 2 tasks in 2026 and an Amtrak memorandum signed that July.
Not in the program
Phase II is a 12- to 16-month local study. It does not award federal planning funds, and it does not hold a place in line.
The Allentown–Bethlehem–Easton metro had 887,615 people in the Census Bureau’s 2025 estimate: third among Pennsylvania metros, behind only Philadelphia and Pittsburgh. A region this size cannot treat a missing train as a nostalgia project.
The point is not to ship workers to New York and leave the wages there. A reliable train makes the Valley easier to hire into. Companies that want New York’s talent pool and the Valley’s costs can put an office here. Hybrid workers can live here and go into the city when the work requires it.
The highway system into New Jersey is the region’s only serious link to the country’s largest job market. A train will not clear every jam. It is the alternative that does not exist. Every year without it, the congestion is the plan.
Allentown, Bethlehem, and Easton can support housing, retail, and offices within walking distance of a platform. New Jersey’s rail-connected towns show what that market looks like. Highway exits do not do the same job.
Places with dependable rail into a major metro keep and attract the higher-wage work tied to that metro.
This was not a surprise. Advocates saw the window coming, the study started too late, and a county funding fight cost another year.
Regular passenger service from the Lehigh Valley to New York ended in 1967. The last passenger train to Philadelphia ran in 1979. Freight kept the corridors. People did not.
Amtrak’s Connects US 2035 vision lists an Allentown–New York route among dozens of proposed corridors. A sketch, not a funded project and not a federal slot.
Scranton already had a rail authority and an Amtrak study underway. Reading’s counties created the Schuylkill River Passenger Rail Authority. The Lehigh Valley had neither.
“We have this year to organize ourselves or we will be left out.”
Joyce Marin, to the Lehigh Valley Transportation Study, May 2022
PennDOT and the Lehigh Valley Transportation Study will study routes, ridership, and costs. Officials say it should take about a year, and that without a study there is no credible federal application.
The first Corridor ID deadline was March 20, 2023. A technical failure led FRA to extend it one week, to 5 p.m. Eastern on March 27. Scranton–New York and Reading–Philadelphia filed. The Lehigh Valley study was not finished. Nothing was submitted.
FRA accepts both corridors. Each is in line for up to $500,000 in initial federal planning funds, plus a defined path and preference for later capital grants. The Lehigh Valley is not on the list.
WSP’s study names five corridors. New York via High Bridge: 2 hours 20 minutes. Planning-level capital costs from $450.3 million to $739 million. A 10- to 12-year build after a project sponsor exists. The sponsor does not exist yet.
The next study is priced around $450,000, to be split by the counties. Lehigh County is ready to pay its share in 2024. Northampton County is not. The work sits for more than a year.
Reset at $400,000: $300,000 in the 2025–26 state budget after a push by State Sen. Nick Miller, and $100,000 from Lehigh County. Northampton County is not a funder. LVPC says 12 to 16 months to identify a preferred route, an operator, and groundwork for a sponsor.
Phase II is the active local study. It is not Corridor ID. Scranton–New York is in Step 2. Reading signed an Amtrak agreement in July. No public announcement has placed the Lehigh Valley in the federal program.
The 2021 infrastructure law created Corridor Identification and Development so new intercity passenger routes would stop living as one-off studies. FRA uses it as the pipeline for projects that might later be built. Getting in does not pour concrete. It does three things that compound.
The December 2023 selections each carried up to $500,000 in planning money for the first step.
Lehigh Valley: Phase I and II paid locally and by the state.
Step 1 scopes the Service Development Plan. Step 2 writes it: route, stations, ridership, railroad agreements, cost. Later steps cover engineering and environment.
Lehigh Valley: not in the sequence.
Projects inside Corridor ID are preferred for later federal construction grants. A region outside is asking to be funded from outside the line.
Lehigh Valley: outside the line.
The March 2023 round is closed. Another round, whenever FRA opens one, will still require a sponsor, a scoped corridor, and local match ready on the day applications are due. That readiness is exactly what 2023, 2024, and 2025 did not produce.
The consultants identified New York as the strongest market. Both New York options use corridors where freight infrastructure largely exists and would need passenger upgrades.
Strongest market, not yet selected
The more direct New York option in the Phase I study. Freight infrastructure is largely in place and needs passenger upgrades, including a longer stretch on Norfolk Southern.
Strongest market, not yet selected
Active rail the whole way: Norfolk Southern toward Phillipsburg, then NJ Transit’s Morris & Essex Line at Hackettstown. Needs NJ Transit and Amtrak cooperation. Operating cost estimated at $23.6 to $28.8 million a year.
Rolling stock on the New York options was estimated separately at about $145 million. Station, financing, and environmental costs are not fully included. Some later news summaries cite a wider band, roughly $552 million to $841 million. All Aboard Lehigh Valley has argued, including before Northampton County Council in April 2026, that the numbers point to New York and that keeping five corridors alive is itself a delay. Phase II is still comparing them.
The Phase I study describes a 10- to 12-year build after a project sponsor exists. Today, none does. Every year we wait to name one moves the first train back by a year. Drag the year to see it.
If a sponsor is named in 2026, the first train runs around 2036 to 2038. Every year without a sponsor adds a year.
Phase II can name a route and an operator. It cannot file an application by itself. Local urgency and matching money have to exist before the next federal window.
2023: No sponsor was readySo no application was filed when the window opened.
2024: One county did not fund the studySo the next phase sat for more than a year.
| Lehigh County | Northampton County | |
|---|---|---|
| Its share of the Phase II study | Paid $100,000 in December 2025 | Did not fund in 2024. Not a funder. |
| A sponsor that can file with FRA | None named | None named |
| Matching funds for a federal application | No public commitment | No public commitment |
| A corridor to pursue | Waiting on Phase II | Waiting on Phase II |
County
Did not fund its share when Phase II was on the table in 2024. A repeat of that gap keeps the region from being ready for the next federal window.
County
Covered the $100,000 local share in December 2025. The next requirement is a sponsor and a budget that survives more than one news conference.
State
The $300,000 state share was written into the 2025–26 budget after State Sen. Nick Miller pushed for it. Later votes decide whether the next application is a priority.
State agency
Paid for Phase I and is lead applicant for Scranton–New York. A Lehigh Valley filing needs the department in the same role, or another sponsor FRA will accept.
Federal
Corridor ID and the capital grants after it are federal. The delegation cannot replace a local sponsor. It can make sure a ready application is not ignored.
Regional
The Lehigh Valley Transportation Study is the region’s metropolitan planning organization, staffed by LVPC. Phase II sits there. So does the decision about who speaks for the corridor.
One list, counted by county, to be presented to the Lehigh County Board of Commissioners and Northampton County Council. It asks for the same three things: a sponsor, a match, and a choice.
Your name is in. Thank you.
That did not go through. Check your name and municipality and try again.
Name a project sponsor that can actually file with FRA.
Put matching funds in both county budgets so 2024 does not happen again.
Say publicly which corridor you will pursue once Phase II reports.
Read the full briefing and send your letter: https://www.lehighvalleytrain.com
Subject: The Lehigh Valley is still outside the federal passenger-rail pipeline
This briefing is independent and not tied to any advocacy group. The fastest way to build pressure is more people asking the same three questions. Send this page to three neighbors, your employer, or your township and borough officials.
Independent public briefing. Not a government site, and not produced by All Aboard Lehigh Valley, PennDOT, or the Lehigh Valley Planning Commission. No party labels. Capital and travel-time figures: WSP, Lehigh Valley Passenger Rail Feasibility Analysis, March 2024. Population: U.S. Census Bureau metro estimate via FRED, 2025.